PMI Project-Management-Professional PMP Question # 900 Topic 91 Discussion

PMP Exam Topic 91 Question 900 Discussion:
Question #: 900
Topic #: 91

The customer's project manager changes during the final stage of a project How can the project manager avoid a project closure delay’


A.

Update the stakeholder engagement plan


B.

Review the latest project status report and update the stakeholders


C.

Escalate the case to the customer's management team


D.

Issue the project payment invoice to the customer in advance