Question #: 943
Topic #: 96

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?


A.

The project charter and scope statement


B.

The requirements traceability matrix


C.

The business requirement documents (BRD)


D.

The WBS dictionary