Question #: 4
Topic #: 1

The project manager is acting as the team manager and needs to control the work of a team member who reports to them.

Which management product should the project manager use to control this work?


A.

A work package description


B.

The project management team structure


C.

A stage plan


D.

A work breakdown structure