Quality control events, such as testing, should be documented in the 'Quality Management Approach' according to PRINCE2® guidelines. This document outlines how quality will be managed throughout the project, detailing specific methods and events, including schedules for quality assurance activities and testing, to ensure that products meet their defined quality criteria.References: = PRINCE2® 7 Foundation Training Manual and official PRINCE2® website documentation