Maintaining the business case during the project lifecycle involves regularly updating it to reflect changes and actual experiences such as incurred costs. This ensures that the project remains viable and aligned with business objectives, as part of the continual justification process. The business case is dynamically managed to reflect any changes in the project's environment and is a fundamental part of the 'business case theme' in PRINCE2.References: PRINCE2® 7 Foundation source documents on business case management.