The purpose of a Risk Register in PRINCE2® is to capture all the risks that may impact the project throughout its duration. It serves as a tool to document the details of each identified risk, including their nature, potential impact, and proposed responses. This register is continuously updated as new risks are identified and as existing risks evolve or are resolved.References: PRINCE2® 7 Foundation handbook and official documents.