To meet the minimum requirements when applying the change theme in PRINCE2®, it is necessary to maintain records of the decisions made on all issues. This includes documenting how each issue was addressed and any subsequent changes made to project plans or products. This record-keeping is crucial for traceability, accountability, and ensuring that decisions are aligned with project objectives and governance.References: PRINCE2® Foundation Manual