The Project Manager role in PRINCE2 is primarily responsible for ensuring that the project produces the required products, to the defined standards of quality and within the specified constraints of time and cost. This central responsibility involves coordinating all project activities and resources to achieve the project objectives.References: PRINCE2® 7 Foundation resources and materials.