Question #: 111
Topic #: 12

Why does the project board review the PID during an end stage assessment?


A.

To confirm that project controls are adequate for the remainder of the project


B.

To notify the commissioning organization that the project has been authorized


C.

To review summarized progress to date and decide what to do next with the project


D.

To ensure that post-project reviews of operational performance are planned