Question #: 114
Topic #: 12

Which statement about the length of management stages in a project is CORRECT?


A.

A higher level of major risk will require a stage to be longer


B.

Stage length is influenced by project board availability


C.

A higher level of major risk will require a stage to be shorter


D.

Use of management stages represents a time driven control