Uncertainty in a project is identified, assessed, and controlled by applying the risk practice. This practice involves systematic risk identification, analysis, and management, ensuring that risks are properly understood and addressed through appropriate responses to protect the project objectives. References: PRINCE2® Foundation official guide and risk management section.