To monitor the progress of a stage effectively, the project manager should review both the Highlight Report and Checkpoint Report. The Highlight Report provides a summary of the stage status to the Project Board, detailing overall progress and identifying any major issues. The Checkpoint Report, on the other hand, offers detailed updates from team managers or team members on the progress of their respective Work Packages. Together, these management products give a comprehensive view of stage progress.References: (PRINCE2® 7 Foundation Handbook, AXELOS)