Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam Prince2-Foundation All Questions
Exam Prince2-Foundation All Questions

View all questions & answers for the Prince2-Foundation exam

PRINCE2 Certification Prince2-Foundation Question # 24 Topic 4 Discussion

Prince2-Foundation Exam Topic 4 Question 24 Discussion:
Question #: 24
Topic #: 4

Thea project manager needs to report to the project board on the status of the project's issues.

Which management product should the project manager review?


A.

Project log


B.

Project brief


C.

Checkpoint report


D.

Highlight report


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.