Approved plans enable control primarily by defining what is included within the approved project scope, which helps to avoid scope creep. These plans establish clear boundaries and deliverables for the project, which are essential for managing resources and ensuring that the project team remains focused on delivering the specified outputs without unnecessary expansion of the project scope.References: (PRINCE2® 7 Foundation Handbook, AXELOS)