In PRINCE2®, the creation of a highlight report is a time-driven control, typically scheduled at regular intervals, such as weekly or monthly during a stage. This report provides the Project Board and other stakeholders with a summary of the stage status, and it is triggered by the passage of time, not by specific events or exceptions within the project.References: = PRINCE2® 7 Foundation Training Manual and official PRINCE2® website documentation