The purpose of the Controlling a Stage process in PRINCE2® is to monitor and control a stage within its authorized tolerances. During this process, the Project Manager assigns work, monitors work progress, deals with issues, reports stage status to the Project Board, and takes necessary corrective actions to stay within the stage's tolerances. References: PRINCE2® Foundation official documentation and study materials.