PRINCE2 Certification Prince2-Foundation Question # 43 Topic 5 Discussion

Prince2-Foundation Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

Which statement about the Directing a Project process is true?


A.

Provides a mechanism for the Project Board to assure that there is continued business justification


B.

Covers the day-to-day activities of the Project Manager


C.

Ensures there are regular progress meetings


D.

Begins on completion of the Initiating a Project process