Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam Prince2-Foundation All Questions
Exam Prince2-Foundation All Questions

View all questions & answers for the Prince2-Foundation exam

PRINCE2 Certification Prince2-Foundation Question # 52 Topic 6 Discussion

Prince2-Foundation Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

Which is NOT considered when defining risk tolerance?


A.

A Project Board's attitude towards risk taking


B.

The allocated risk budget


C.

An organization's risk appetite


D.

The amount of risk a Project Board considers acceptable


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.