When defining risk tolerance, the factors considered include the Project Board's attitude towards risk, the organization's risk appetite, and the level of risk deemed acceptable by the Project Board. The allocated risk budget is not a direct consideration in defining risk tolerance; rather, it is a resource aspect managed within the tolerances set for the project. References: PRINCE2® Foundation Training Manual; PRINCE2® 2017 Foundation handbook.