The statement that the quality review technique defines the quality responsibilities of the project team is false. The quality review technique in PRINCE2 primarily focuses on checking the product's fitness for purpose, involving key parties to gain wider acceptance, and providing a baseline to manage future changes, but does not specifically define the quality responsibilities of the team. References: PRINCE2® Foundation Training Manual; PRINCE2® 2017 Foundation handbook.