What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products


A.

1 and 2


B.

2 and 3


C.

3 and 4


D.

1 and 4