The minimum requirement for applying the Plans Theme in PRINCE2 is following the product-based planning approach. This approach involves creating a product breakdown structure, writing product descriptions, and defining product dependencies before developing the schedule and resource plans. It ensures that plans are focused on the project's deliverables and their quality requirements. References: PRINCE2® 7 Foundation Handbook and official training materials.