PRINCE2 Certification Prince2-Practitioner Question # 22 Topic 3 Discussion

Prince2-Practitioner Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.''

In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''.

Is this appropriate, and why?


A.

Yes, because delivering incrementally will reduce the impact of the threat.


B.

Yes, because a risk response needs to be implemented for this major threat.


C.

No, because risks responses should be identified as part of the 'plan' step.


D.

No, because a risk action should be allocated to implement a response.