Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam Prince2-Practitioner All Questions
Exam Prince2-Practitioner All Questions

View all questions & answers for the Prince2-Practitioner exam

PRINCE2 Certification Prince2-Practitioner Question # 38 Topic 5 Discussion

Prince2-Practitioner Exam Topic 5 Question 38 Discussion:
Question #: 38
Topic #: 5

The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.

Which 2 actions should the Team Manager take in response to this situation?


A.

Ask the reviewers to work overtime to prevent the delay.


B.

Ensure that the situation is included in the next Highlight Report.


C.

Raise an issue explaining that tolerances are forecast to be exceeded.


D.

Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.


E.

Ensure that the Quality Register is updated with the quality review result.


Get Premium Prince2-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.