PRINCE2 Certification Prince2-Practitioner Question # 64 Topic 7 Discussion

Prince2-Practitioner Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

While preparing the Quality Management Strategy, the Project Manager noticed that the corporate quality management system does not specifically cover project management.

Which option provides an appropriate way for the Project Manager proceed?


A.

Record the development of a corporate quality management system for project management as a prerequisite of the Project Plan.


B.

Proceed with the project without a Quality Management Strategy and adopt the selected service provider's standards in stage 4.


C.

Seek relevant organizational standards, then facilitate a workshop to discuss the Quality Management Strategy with Project Assurance.