Which of the following management products ARE updated as part of Managing a stage boundary?

1. Business Case

2. Benefits Review Plan

3. Configuration Item Records

4. Project Brief


A.

1, 2, 3


B.

1, 3, 4


C.

1, 2, 4


D.

2, 3, 4