Question #: 45
Topic #: 5

A nonprofit realizes that the target deployment date is concurrent with a Salesforce major seasonal release window.

Which two steps should the nonprofit take when finalizing the plan for the new feature in production?

Choose 2 answers


A.

Verify the sandbox Is on the same release as production.


B.

Log a Salesforce support case to change the version of the sandbox release.


C.

Deploy a Change Set during the upgrade window for the production instance.


D.

Review the sandbox preview instructions for the upcoming release.