Scaled Agile SA - SAFe Agilist SAFe-Agilist Question # 7 Topic 1 Discussion

SAFe-Agilist Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

The analyzing step of the Portfolio Kanban system has a new Epic with a completed Lean business case. What best describes the next step for the Epic?


A.

It will be implemented once the Epic Owner approves the Lean business case


B.

It will be implemented if it has the highest weighted shortest job first (WSJF) ranking


C.

It will be moved to the ready state in the Portfolio Kanban if it receives a 'go' decision from Lean Portfolio Management


D.

It will remain in the analyzing step until one or more Agile Release Trains have the capacity to implement it