A confidence vote is taken at the end of PI Planning after dependencies are resolved and risks are addressed. What best describes the process of the confidence vote?
According to the SAFe Agilist 6.0 domain of PI Planning, the confidence vote is a process where:
Each team conducts a vote using their fingers (fist of five) or a digital tool for remote events
The teams vote on the confidence level for the objectives as a set, and if confidence is high enough, the aggregate set of objectives becomes the committed ART plan
The Release Train Engineer summarizes the team objectives into the ART PI objectives in a format suitable for management communication
https://scaledagileframework.com/pi-planning/