Scaled Agile Framework SAFe-RTE Question # 69 Topic 3 Discussion

SAFe-RTE Exam Topic 3 Question 69 Discussion:
Question #: 69
Topic #: 3

Which of the following is true about the ART sync event?


A.

It is run after PO-sync and Scrum of Scrum events


B.

It is a combination of PO-sync and Scrum of Scrums events


C.

It occurs during the Innovation and Planning iteration


D.

Attendance by the entire ART is important