Scaled Agile Framework SAFe-RTE Question # 45 Topic 5 Discussion

SAFe-RTE Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

What is one technique for building a one-team culture across the ART?


A.

Ensure the team leader does not show vulnerability


B.

Rotate team members to new teams to facilitate relationship building


C.

Foster an environment in which the whole ART succeeds and fails together


D.

Review each teams' predictability measure with the ART