Scaled Agile Framework SAFe-RTE Question # 106 Topic 7 Discussion

SAFe-RTE Exam Topic 7 Question 106 Discussion:
Question #: 106
Topic #: 7

How can a Release Train Engineer support decentralized decision making?


A.

Update team Program Increment (PI) Objectives when shipping a time critical re-lease


B.

Empower knowledge workers to manage their dependencies with other teams


C.

Evaluate the strategy for the Value Stream


D.

Change the cadence of the Agile Release Train