Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PSD All Questions
Exam PSD All Questions

View all questions & answers for the PSD exam

Scrum Professional Scrum Developer PSD Question # 4 Topic 1 Discussion

PSD Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

How much time will there be after a sprint before the next one starts?


A.

Enough to deploy the increment and update the product backlog based on the outcome of the sprint review


B.

Enough to clean up lingering definition of done points


C.

None, a new sprint starts immediately after the end of the previous one


D.

At most a week for a one-month sprint


Get Premium PSD Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.