Scrum Professional Scrum Developer PSD Question # 9 Topic 1 Discussion

PSD Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

Which output from sprint planning provides the developers with a target and overarching direction for the sprint?


A.

The sprint backlog


B.

The product goal


C.

The Sprint goal


D.

Sprint review minutes