Question #: 35
Topic #: 4

Which concept is described by the Last Responsible Moment? (choose the best answer)


A.

Discover decisions to be made as soon as possible but postpone making those decisions until the latest reasonable moment.


B.

Making decisions as soon as possible to close feedback loops as soon as possible.


C.

The last moment in a Sprint when code changes are allowed; after this, only stabilization work should be conducted.


D.

The last moment a Developer is responsible for quality; after this, the Tester is responsible.