Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PSD All Questions
Exam PSD All Questions

View all questions & answers for the PSD exam

Scrum Professional Scrum Developer PSD Question # 38 Topic 4 Discussion

PSD Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

Developers are blocked by an impediment in the middle of the Sprint. The impediment is outside the Developer’s control. What should they do? (choose the best answer)


A.

Cancel the Sprint.


B.

Immediately raise the issue to the Scrum Master.


C.

Complete the work that can be done and complete the remainder during the "hardening sprint".


D.

Stop using Scrum until the impediment is resolved.


E.

Drop the Product Backlog items affected by the impediment from the Sprint Plan.


Get Premium PSD Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.