Scrum Professional Scrum Developer PSD Question # 42 Topic 5 Discussion

PSD Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

What happens if the Scrum Team cannot complete its work by the end of the Sprint? (choose the best answer)


A.

The Sprint is extended temporarily. Lessons are taken to ensure it does not happen again.


B.

The Sprint length is unchanged, and the Scrum Team continuously learns and adapts.


C.

The Sprint is extended, and future Sprints use this new duration.