Scrum Professional Scrum Developer PSD Question # 45 Topic 5 Discussion

PSD Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

How much time does Product backlog refinement take?


A.

25% of the sprint capacity


B.

As much as needed without endangering the Sprint goal


C.

10% of the senior developers