According to the Scrum Guide, Developers do meet with stakeholders, especially during the Sprint Review and Sprint Planning events. The Product Owner is the primary person who interacts with stakeholders, but Developers also need to communicate with them to understand their needs, expectations, and feedback. The Product Owner may also invite stakeholders to provide clarifications or inputs during the Sprint.