A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation?
(Choose two.)
A.
Discuss the impediments with the Development Team.
B.
Prioritize the list and work on them in order.
C.
Arrange a triage meeting with all project managers.
Two techniques that would be most helpful in this situation are to discuss the impediments with the Development Team, and to prioritize the list and work on them in order, as stated in [3]: “The Scrum Master should facilitate a discussion with the Development Team to identify and prioritize the impediments that are blocking their progress. The Scrum Master should then work with the Development Team and other stakeholders to remove or mitigate these impediments as soon as possible.”
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit