The correct answer is B, because when multiple Scrum Teams work from the same Product Backlog, they should pull in work in agreement with the Product Owner. The Scrum Guide states that “multiple Scrum Teams often work together on the same product. One product goal unites them. Therefore, they must mutually define and comply with a definition of ‘Done’ that applies to their combined work product.” Therefore, they should collaborate and coordinate with each other and with the Product Owner to select Product Backlog items that align with their shared product goal.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit