Scrum Professional Scrum Master I PSM-I Question # 29 Topic 3 Discussion
PSM-I Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3
A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?
A.
The hiring manager is responsible, because he/she hired the developer.
B.
The Scrum Manager is responsible, because he/she removes Impediments.
C.
The Development Team is responsible, and may need help from the Scrum Master.
D.
The Product Owner is responsible, because he/she controls the return on investment (ROI).
The correct answer is C, because if necessary, the Development Team is responsible for removing a team member who is creating a hostile environment. The Scrum Guide states that “development Teams are self-organizing. No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality.” Therefore, the Development Team should manage its own composition and dynamics, and may need help from the Scrum Master to facilitate this process.