Who creates the definition of “Done”?


A.

The Scrum Master as he/she is responsible for the Development Team’s productivity.


B.

The Scrum Team, in a collaborative effort where the result is the common denominator of all members’ definition.


C.

The Product Owner as he/she is responsible for the product’s success.


D.

The development organization (or Development Team if none is available from the development organization).