Scrum Professional Scrum Master PSM-I Question # 60 Topic 7 Discussion

PSM-I Exam Topic 7 Question 60 Discussion:
Question #: 60
Topic #: 7

When does the next Sprint begin?


A.

When the Product Owner is ready.


B.

Immediately after the conclusion of the previous Sprint.


C.

The Monday following the Sprint Review.


D.

Immediately following the next Sprint Planning.