The Scrum Master should ask the person to share the issue with the team as soon as possible, as stated in [5]: “The Scrum Master should encourage transparency and collaboration within the team and with other stakeholders. If there is a concern about data security issues, it should be brought up to the team and discussed openly. The team can then decide how to handle it, whether by creating a Product Backlog item, updating the definition of “Done”, or taking some other action.”