Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PSM-I All Questions
Exam PSM-I All Questions

View all questions & answers for the PSM-I exam

Scrum Professional Scrum Master PSM-I Question # 68 Topic 7 Discussion

PSM-I Exam Topic 7 Question 68 Discussion:
Question #: 68
Topic #: 7

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)


A.

Recruit additional Developers before the work can begim


B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.


C.

The Developers work overtime during this Sprint


D.

Cancel the Sprint


E.

Remove or change selected Product Backlog items.


Get Premium PSM-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.