Scrum Professional Scrum Master PSM-I Question # 77 Topic 8 Discussion

PSM-I Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)


A.

Inform the Product Owner’s functional manager.


B.

Stop the Sprint, send the Product Owner to a course and restart.


C.

Bring up the problem in the Sprint Retrospective.


D.

Coach the Product Owner in the values of Scrum and incremental delivery.


E.

Nominate a proxy Product Owner.