Scrum Professional Scrum Master PSM-I Question # 80 Topic 9 Discussion

PSM-I Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?


A.

The Sprint Backlog.


B.

The Sprint Goal


C.

The release plan.


D.

Sprint Review minutes.