Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PSM-II All Questions
Exam PSM-II All Questions

View all questions & answers for the PSM-II exam

Scrum Professional Scrum Master PSM-II Question # 2 Topic 1 Discussion

PSM-II Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

You are the Scrum Master for three Scrum Teams working on the same product. There is a single Product Backlog that all three Scrum Teams select from. Management is eager to improve the productivity of the teams and wants to standardize velocity across all three teams so that they can see how each team is delivering value. When responding to management, which two statements are appropriate?

(choose the best two answers)


A.

Incentivizing teams based on velocity can boost the Scrum Team's motivation to create more value.


B.

Standardizing velocity across teams can help with understanding which teams

are creating more value.


C.

Velocity has no direct relationship with value.


D.

Velocity is the amount of business functionality that a Scrum Team creates in a Sprint. It is unique to that team and used as an input to Sprint Planning.


Get Premium PSM-II Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.