PSM-II Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

Which statements are true about the Sprint Goal?

(choose the best two answers)


A.

Sprint Goals often change during the Sprint as new insights emerge during the work.


B.

During Sprint Planning, the Scrum Team crafts a Sprint Goal based on anobjective that the Product Owner would like to achieve that Sprint.


C.

Sprint Goals give Developers flexibility and creativity on how to implement functionality during the Sprint


D.

The use of Sprint Goals is optional in the Scrum Framework