During the Sprint Review of a scaled development effort, the Scrum Teams should demonstrate the integrated Increment that they have collectively delivered, not their individual Increments separately. This ensures that the stakeholders can provide feedback on the value and quality of the product as a whole, and that the Scrum Teams can inspect their alignment and collaboration.
References:
Scrum Guide 2020, page 14: “The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. The Scrum Team presents the results of their work to key stakeholders and progress toward the Product Goal is discussed.”
Nexus Guide 2020, page 7: “The Nexus Sprint Review is an event where appropriate stakeholders review the Integrated Increment that has been built throughout the Sprint by all Scrum Teams in a Nexus.”